The project involved a multiple of items / tasks, firstly stripping out the derelict charring cross underground entrances on William IV St, Adelaide St & the Strand and installing steel escape entrances with perforated panels. 

Along William IV St we had multiple shopfronts to renovate by introducing an aluminum clad upstand to prevent homeless from taking refuge as this was an issue for the bank.

Lastly installing a new perforated steel screen with a Dry riser at the end of William IV St. 

Project Info

System:

Forster Presto 50 steel doors / Swegon NACO 75 louvres 

Location:

London

Project Date:

2023